Current Projects




Soghri Development project

06/22/2015

The Soghri field is located in Jand District, Punjab Province. The scope of work for this project involves the installation of 40 MMscfd Gas Sweetening Amine Plant and allied utilities at Dakhni Plant. The projected product yield upon completion is 15 MMscfd per day of gas and will be enhanced to 30 MMscfd upon completion of additional wells. The Amine plant has been shifted at Soghri site. Procurement of additional equipment is in progress. Hiring the services of PC Contractor for installation of plant in progress.

This project will enhance Dakhni Plant capacity Gas Sweetening capacity from 40 MMscfd to 80 MMscfd. The new unit will process Soghri Gas & the Old Plant will process Gas from Jand and Dakhni. 
 

 

Read More

Project Future

11/25/2014

aas

Read More

Dakhni Expansion Project

11/25/2014

The Dakhni gas processing plant was commissioned in 1989 with a design capacity of 30 MMscfd of sour feed gas. Over its years in production, the composition of H2S contents in the raw gas has significantly increased, resulting in limited production capabilities. The Dakhni Expansion Project was planned & implemented to increase the gas handling capacity from 30 to 40 MMscfd and additional Sulphur Recovery Unit (SRU) of 90 MTon/Day has also been installed. The activities were completed in May 2013. 

The improvement in Utility System by Power Turbine and Refrigeration Package installation is nearing completion.

Read More

Jhal Magsi Development Project

08/05/2014

Jhal Magsi gas field is located in District Jhal Magsi Baluchistan, and is a joint venture among OGDCL (56%), POL (24%), GHPL (20%), with OGDCL serving as the operator. The development project involves installation of dehydration/compression/ H2S removal plant to produce 15 MMscfd pipeline quality sales gas.

The project activities are on-hold due to delay in laying of sales gas line by SSGCL

Read More

Nashpa/ Mela Development Project

08/04/2014

Nashpa-Mela fields are located in Karak & Kohat Districts of KPK  province. OGDCL is the operator of these fields while other JV partners include Pakistan Petroleum Limited (PPL) and GHPL. Development of both the projects is under implementation phase. As per development plan, a centralized gas processing & LPG plant will be installed at Nashpa field. The crude stabilization and gas compressor will be installed at Mela. The gas of Mela will also be transported to Nashpa for extraction of LPG.

The contract has been signed on EPCC basis with M/s Hong Kong Hui Hua design/ supply/ installation and commissioning of Gas Processing & LPG Recovery Plants, Sales Gas Compressors and Allied Facilities at Nashpa Field. The expected incremental Production upon the completion from Nashpa & Mela will be: Gas: 10 MMscfd, Condensate: 1120 bbls/day and 370 Mton/Day of LPG. 

Read More

Uch-II Development Project

08/04/2014

The Uch gas field is located about 67 km southeast of Dera Bugti in Baluchistan province. To date we have drilled 36 wells and we are currently supplying 220-225 MMscfd per day to Uch Power Ltd. via a 47 km pipeline at the first mega low heating value gas-fired 586 MW power plant. After completing a detailed study of the Uch gas field, OGDCL adopted a development plan under which production at the Uch gas field is to be increased from 220 to 380 MMscfd per day, enabling us to commit 160 MMscfd per day of gas for 25 years to a new power producer. This project involves installation of a gas gathering facility and installation of dehydration and hydrogen sulphide, (H2S), removal plant and gas delivery Station. GSA with UPL has been signed.

Through the contingent plan, OGDCL is supplying gas to UPL on daily basis as per their demand since Feb 2014. However, OGDCL will complete its new processing facilities soon which will further help to maintain gas supply to UPL.

Main Project: The Procurement process of most of the long lead Equipments’ has been completed. Deliveries of various packages have been arrived and erected on the foundations. The Contract of PC Contractor for Plant construction has been signed with To M/s TDE-Zealcon Consortium on 22.07.2013. The PC Contractor mobilized at site and the work has been started. The project would be completed by September, 2014..

Read More